Past Projects

One of the best ways to analyze a General Contractor is to evaluate their past performance.

 

Client:

Contact:

bionet-asia.com

Type of Business:

Biological Pharmaceutical

Project Title:

 

Location:

Hi-Tech Industrial Estate, Ayuthaya, Thailand.

Dates:

Phase 1: June 2007 – July 2008

Phase 2: May 2010 - Oct 2010

Flood recovery: Jan 2012 - Jun 2012

Cleanroom upgrade: Feb 2017 – Jun 2018

Scope of services:

Detailed Engineering Design, Construction Management, Procurement Management, Commissioning and Validation.

Area Size:

Phase 1: 800sqm

Phase 2: 900sqm

Flood recovery: 900sqm

Cleanroom upgrade: 1,800sqm

Project Profile:

title_673a9b04dda928611221591731894020
title_673a9b04ddb099638561461731894020
 

Project Highlights

  • Cleanroom & Internal architectural works
  • B1 Building: Administrative and QC building.
  • B2 Building: aP Vaccine production, Cleanroom Grade B,C and D.
  • B3 Building: R&D Cleanroom Grade C and D.
  • B8 Building: Process Utilities (Purified water, Pure steam, WFI, Clean dry air, Decontamination
  • Electrical works ( EMS, BMS, Power, Lighting, Fire alarm, Security & access control, CCTV, Lightning & grounding, etc.)